Brooks City Base

Location

San Antonio – TX

DATE DELIVERED

January 15, 2023

Type of Work

Installation of Electrical Underground Infrastructure

Budget

$180K

Project Description

 This project included installation of 600 linear feet of underground conduit duct bank, eight vertical risers, two 7′ x 7′ x 7′ precast manholes, and two reinforced concrete transformer oil‑containment slabs with pit systems. These components were installed to support the new step‑up transformer configuration and ensure compliance with electrical and environmental standards.